Infos from an AIB Scheduled
------------------------------------------------------------------------------
BOM Release Bill Of Materials Release beginning to end of June
EVT Engineering Validation Test end of June to beginning of July
DVT Design Validation Test beginning to middle of July
WS Working Sample middle of July
(still with engineering hardware
& software)
EMI Test Electromagnetic Interference Test middle of July
PVT Production Validation Test end of July to beginning of
August
PVT Sorting ? beginning of August
PPBIOS final source BIOS from AMD beginning of August (August 2)
Ramp & MP Mass Production no timetable, awaiting further
info from AMD
PS: And custom designs should not be awaited before middle to end of August
(as earliest).
--
adeon-rx-vega
縮網址:https://goo.gl/ouzBQn
英文翻譯:https://goo.gl/YR2snM
--
Infos from an AIB Scheduled
------------------------------------------------------------------------------
BOM Release Bill Of Materials Release beginning to end of June
EVT Engineering Validation Test end of June to beginning of July
DVT Design Validation Test beginning to middle of July
WS Working Sample middle of July
(still with engineering hardware
& software)
EMI Test Electromagnetic Interference Test middle of July
PVT Production Validation Test end of July to beginning of
August
PVT Sorting ? beginning of August
PPBIOS final source BIOS from AMD beginning of August (August 2)
Ramp & MP Mass Production no timetable, awaiting further
info from AMD
PS: And custom designs should not be awaited before middle to end of August